regasification
Regasification service offered by Adriatic LNG includes:
- Availability of terminal capacity
- Mooring of LNG carriers
- LNG unloading
- Storage
- Redelivery of corresponding LNG units in Cavarzere, admittance point of the national network.
Every year during the months of June and July, Adriatic LNG offers its capacity for mid- and long-term periods (up to ten years) and on a monthly basis with infra-annual capacity (until the end of current thermal year, which is September 30th, 2017).
Check pricing for regasification service for the period concerned.
24 May 2016
Publication of the Terminal regasification Capacity in accordance with the Article 2.4.2. of Chapter II of the Regasification Code.
According to the Article 2.4.2 of Chapter II of the Regasification Code, Adriatic LNG publishes the Terminal regasification Capacity.
The Terminal Capacity is determined by considering the technical and operational limits of the Terminal and taking into account the number and duration of Unloading Slots, Storage capacity, send-out capacity and the available pipeline capacity at the Cavarzere Entry Point.
For more details see Article 2.1 of Chapter II of the Regasification Code.
TERMINAL REGASIFICATION CAPACITY
Period: 10 Thermal Years
1 T.Y. from 1° October 2016 to 30 September 2017 | ||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Terminal Regasification Capacity (a) |
|
|||||||||||||||||||||
Not Available for Subscription (b) |
|
|
||||||||||||||||||||
Available for Subscription (c = a - b) |
|
|
2 T.Y. from 1° October 2017 to 30 September 2019 | ||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Terminal Regasification Capacity (a) |
|
|||||||||||||||||||||
Not Available for Subscription (b) |
|
|
||||||||||||||||||||
Available for Subscription (c = a - b) |
|
|
1 T.Y. from 1° October 2019 to 30 September 2020 | ||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Terminal Regasification Capacity (a) |
|
|||||||||||||||||||||
Not Available for Subscription (b) |
|
|
||||||||||||||||||||
Available for Subscription (c = a - b) |
|
|
6 T.Y. from 1° October 2020 to 30 September 2026 | ||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Terminal Regasification Capacity (a) |
|
|||||||||||||||||||||
Not Available for Subscription (b) |
|
|
||||||||||||||||||||
Available for Subscription (c = a - b) |
|
|
(1) Liquid to gas coefficient, density value and gross calorific value are based on historical / contractual data
(2)Indicative number of Unloading Slots
(3) Unsubscribed Exempted Capacity reclassified as Unsubscribed Regulated Capacity for the purpose of the Annual Subscription Process according to the Regasification Code chapt. II par. 2.4.2
(4) Released Exempted Capacity reclassified as Released Regulated Capacity for the purpose of the Annua l Subscription Process according to the Regasification Code chapt. II par. 2.4.2
(5) Following the expiry of a Contract for Regulated Capacity, the following additional Slots are avail able starting from 2020, on top of the Slots available in the period October 2015 -
- 9 addtional Slots for each T.Y. are available starting from January 2020
- 3 addtional Slots for each T.Y. are available starting from October 2020
04 July 2016
Annual Subscription Process for the period of Thermal Year 2016/2017 to Thermal Year 2026/2027 inclusive - Update July 4th 2016: Conclusion of Annual Subscription Process.
- Courtesy English Translation (not binding – only the Italian version is binding) –
Adriatic LNG has received no requests by the deadline of 17:00 CET Wednesday July 1st 2016 for the Annual Capacity Subscription process.
The allocation procedure of the following Available Capacity will be opened within the Monthly Capacity Subscription process starting from July 22nd , 2016 at 17:00 CET.
Thermal Year (TY) | Number of Unloading Slots | Month | Period of slot discharge |
---|---|---|---|
2016/2017 | 1 | September 2016 | 16 - 19 September |
2016/2017 | 1 | October 2016 | 13 - 16 October |
2016/2017 | 1 | October 2016 | 21 - 24 October |
2016/2017 | 1 | November 2016 | 14 - 17 November |
2016/2017 | 1 | December 2016 | 27 – 30 December |
2016/2017 | 4 | Period January-September 2017 | To be defined (*) |
(*)To be determined based on estimates of Chapter II, Section 3.2 - Annual Scheduling of the Regasification Code
24 May 2016
Annual Subscription Process for the period of Thermal Year 2016/2017 to Thermal Year 2025/2026 inclusive – Rules for the Annual Subscription Process of Available Regasification Capacity in accordance with Article 8.7 of the Resolution of the Authority for Electricity and Gas No 168/06 and Article 2.4.2 of Chapter II of the Regasification Code.
- Courtesy English Translation (not binding – only the Italian version is binding) –
With reference to the regasification Capacity of the Terminal published on this website on May 24th, 2016 en > Business > Regasification service > THERMAL YEAR 2016 2017 > Regasification capacity Adriatic LNG offers, under the Annual Subscription Process, Available Regulated Capacity for the period of Thermal Year 2016/2017 to Thermal Year 2025/2026 inclusive.
Access Requests should be sent to ALNG by no later than 17:00 C.E.T. of 1st (first) July 2016.
For more information or clarifications, please contact:
Dr.ssa Roberta Pirotta, Tel.: +39.02.63698569, Email : roberta.pirotta@adriaticlng.it
Ing. Dahm Gazzola Riccardo, Tel.: + 39.02.63698572, Email : riccardo.dahm.gazzola@adriaticlng.it
Annual Subscription Process for the period of Thermal Year 2016/2017 to Thermal Year 2025/2026 inclusive – Terminal regasification Capacity
Rules for the Annual Subscription Process of Available Regasification Capacity in accordance with Article 8.7 of the Resolution of the Authority for Electricity and Gas No 168/06 and Article 2.4.2 of Chapter II of the Regasification Code.
21 Aug 2017
Terminale GNL Adriatico ("the Operating Company" or "Adriatic LNG") make available for subscription during the Infra-Annual Subscription Process ‐ Second Phase (“first come first served”), the following Available Capacity:
Service type | Month | Unloading Slot Period |
Scheduled Arrival range |
Volume of LNG (Liquid m3) |
Deadline for the submission of the Access Request |
Capacity: Released/Available |
---|---|---|---|---|---|---|
spot | August-September | 30 August - 1 September | 30 – 31 August | 145.000 | 23 August 2017 | Available |
continuous | December | 7 – 10 December | 7- 8 December | 145.000 | 15 September 2017 | Available |
continuous | January-September 2018 | to be defined | to be defined | 5 x 145.000 | 15 September 2017 | Available |
18 Aug 2017
Terminale GNL Adriatico ("the Operating Company" or "Adriatic LNG") make available for subscription during the Infra‐Annual Subscription Process - First Phase, the following Available Capacity:
Service type | Month | Unloading Slot Period |
Scheduled Arrival range |
Volume of LNG (Liquid m3) |
Deadline for the submission of the Access Request |
Capacity: Released/Available |
---|---|---|---|---|---|---|
spot | August-September | 30 August - 1 September | 30 – 31 August | 145.000 | 20 August 2017 | Available |
continuous | December | 7 – 10 December | 7- 8 December | 145.000 | 20 August 2017 | Available |
continuous | January-September 2018 | to be defined | to be defined | 5 x 145.000 | 20 August 2017 | Available |
This publication in conjunction with conditions published under Rules/tariffs are an integral and substantial part of the capacity offer under the Infra‐annual Subscription process. A copy of the publications above must be signed by the legal representative of the Applicant and be delivered in conjunction with the Access Request.
RELATED
Infra-Annual Subscription Process November (22 kByte - pdf) » Infra-Annual Subscription Process December (102 kByte - pdf) » Infra-Annual Subscription Process January (99 kByte - pdf) » Infra-Annual Subscription Process February (19 kByte - pdf) » Infra-Annual Subscription Process March (99 kByte - pdf) » Infra-Annual Subscription Process April (74 kByte - pdf) » Infra-Annual Subscription Process May (102 kByte - pdf) » Infra-Annual Subscription Process Jun (102 kByte - pdf) » (102 kByte - pdf)Infra-Annual Subscription Process Jul (16 kByte - pdf) »
15 May 2015
SCHEDULE OF UNLOADING SLOTS
The calendar displays the unloading slots allocated and available for subscription in the year 2017 (pursuant to Article 3, Chapter II of the Regasification Code).
KEY:
Subscribed Capacity
Available Capacity
1) Assignment of unloading slots takes place during the quarterly scheduling process.
1) Terminale GNL Adriatico (the "Operating Company" or "Adriatic LNG") makes available for subscription the following Available Capacity, as published on the Electronic Communication System.
The publication of the Infra-Annual Capacity Subscription Process must be signed by the legal representative of the Applicant and be delivered in conjunction with the Access Request.
2) The applicable tariff by the Operating Company is the Regasification and Metering Tariffs in force for the relevant period, as published on the Adriatic LNG website and herein attached (“Annex Tariff”).
From January 1st 2016 to December 31st 2016 Tariff 2016
From January 1 2017 to December 31st 2017 Tariff 2017
The above attachment shall be signed by the legal representative of the Applicant and delivered together with the Access Request.
3) The are one or potentially two phases of the Infra-Annual Capacity allocation process.
First phase
The Access Requests must be sent to Adriatic LNG by registered mail or fax by and not later than 17:00 CET of the “deadline” as of point v) lett. (e) comma 3 of the Article 2 Chapter II of the Regasification Code at the following address:
Terminale GNL Adriatico S.r.l
Piazza S. Freud 1
20154 Milano (MI), Italy
Fax +39.02.44386377
Infra-Annual Capacity allocation process– first phase
4) If the access request is sent by fax, the original documentation shall be sent in due time by registered mail or hand delivered no later than the 17:00 CET the following business day from the deadline pain of inadmissibility of the request.
5) The request is binding, irrevocable and unconditional up to 17:01 CET of the working day following the Deadline.
6) The Operating Company undertakes to notify Applicants of the results (acceptance or reject) with reference to each Access Request by 17.00 CET of the Day 20th of each Month.
7) Instructions for Access Requests, Allocation Criteria and Access Conditions are provided in the applicable rules and in the Regasification Code. The Regasification Code is an integral part of the Capacity Agreement.
8) The Regasification Code approved by the Authority for the electricity gas and water system with Resolution Arg/Gas n. 57/11 and the following updates is available at the following link: Codice di Rigassificazione di Terminale GNL Adriatico.
9) The provisions of this publication are an integral and substantial part of the Infra-Annual Capacity Subscription offer. Copy of this publication, in the form attached, must be signed by the Legal Representative of the Applicant and be delivered in conjunction with the Access Request. Infra-Annual Capacity Subscription Process - TY 2016/2017 – Rules/tariffs .
Second phase: first come first served.
1. If by the Deadline all the Infra-Annual Capacity has not been allocated, the Operating Company will assign the Available Capacity in accordance with the “first come first served" rules.
In this case, Access Requests shall be sent by registered mail or fax on business days following the Deadline from 8.30 to 17.00 C.E.T. up to:
• 5th Working Day prior to the Scheduled Arrival Range of each Unloading Slot, for the Spot Capacity; and
• 15th Day of the Month following the publication of the Infra-Annual Capacity, for the Continuous Capacity.
The Access Requests must be sent to Adriatic LNG at the following address:
Terminale GNL Adriatico S.r.l
Piazza S. Freud 1
20154 Milano (MI), Italy
Fax +39.02.44386377
Infra-Annual Capacity Subscription Process – Second phase
2. If the access request is sent by fax, the original documentation shall be sent in due time by registered mail or hand delivered no later than the 17:00 CET the following business day from the deadline pain of inadmissibility of the request
3. The request is binding , irrevocable and unconditional up to 17:01 CET of the 2nd working day following the delivery date of the Access Request
4. The Operating Company undertakes to notify Applicants of the results (acceptance) by 17.00 CET of the working day following the delivery date of the Access Request.
5. Instructions for Access Requests and Access Conditions are provided in the applicable rules and in the Regasification Code. The Regasification Code is an integral part of the Capacity Agreement.
6. The Regasification Code approved by the Authority for the electricity gas and water system with Resolution Arg/Gas n. 57/11 and the following updates is available at the following link: Codice di Rigassificazione di Terminale GNL Adriatico.
7. The provisions of this publication are an integral and substantial part of the Infra-Annual Capacity Subscription offer. Copy of this publication, in the form attached, must be signed by the Legal Representative of the Applicant and be delivered in conjunction with the Access Request. Infra-Annual Capacity Subscription Process - TY 2016/2017 – Rules/tariffs